// CONCRETE · METHOD & WORKED EXAMPLE

How much concrete for a slab?

Turn slab length, width and thickness into cubic yards, then into bags or a ready-mix order.

THE FORMULA

Cubic feet = L × W × (thickness in ÷ 12) · Cubic yards = cu ft ÷ 27

// HOW TO CALCULATE

Step by step.

  1. Measure the slab length and width in feet, and decide the thickness in inches (often 4 in for patios and walks).
  2. Multiply length × width × thickness ÷ 12 to get cubic feet.
  3. Add 5–10% for uneven ground and spillage.
  4. Divide cubic feet by 27 for cubic yards, or by the bag yield for bags (an 80 lb bag makes about 0.60 cu ft).

// WORKED EXAMPLE

The numbers.

EXAMPLE

A 12 × 10 ft patio at 4 in is 12 × 10 × 0.333 = 40 cu ft. With 10% extra that is 44 cu ft, or 1.63 cubic yards. In 80 lb bags: 44 ÷ 0.6 = 74 bags, about $518 at $7 a bag.

Try it with your numbers →

// TIPS

Before you buy.

  • Above roughly 1 cubic yard, ready-mix delivery is usually easier than mixing bags; most trucks carry about 9–11 cubic yards.
  • Compact the base and set forms level before ordering, so the thickness you calculated is the thickness you pour.
  • Order a little extra: running short leaves a weak cold joint.

Sources and further reading

These are explanatory examples, not engineering advice, live price quotes, or guarantees of product yield. Consult manufacturer instructions, local codes and qualified professionals where necessary.