How to build a renovation contingency budget

Keep planned costs, actual spending and contingency separate so the project stays understandable.

// HOW TO CALCULATE

Step by step.

  1. List project categories and obtain written quotes or supplier prices.
  2. Record planned costs for each category and total them.
  3. Add a separately identified contingency reserve based on the project’s uncertainty.
  4. Track actual spending and compare it with planned amounts, including the reserve.

// WORKED EXAMPLE

The numbers.

EXAMPLE

For a $4,850 planned budget and a 10% reserve, the contingency is $485 and the planning ceiling is $5,335. If actual costs reach $4,000, $1,335 remains including reserve.